The project included the installation of APS electrical /CenturyLink communication and Cox Communication duct bank that replaced the existing utilities that were in the new roadway grade. This project was in conjunction with the City of El Mirage project, “El Mirage Road Improvements – Cinnabar to Cactus.” This project included APS power, COEM street lighting, CenturyLink Communications and Cox Communication. The APS Conduit size ranged from 2” to 5” including Primary and Secondary electric along with 1.25” Quad Duct for Interconnect and (6) 2” conduit for Cox Communication. The project went through multiple design meetings prior to the start of construction. The design meetings included the partners of APS, CenturyLink, Cox and the City of El Mirage and Sunland Asphalt.
City of El Mirage
El Mirage, AZ
Copyright 2022 • Sunland Asphalt & Construction, LLC
Copyright 2022
Sunland Asphalt & Construction, LLC