Description

The project at Breakthru Beverage in Las Vegas, NV consisted of a complete removal and replacement of approximately 12,577 square feet of failed asphalt, including 526 linear feet of cracks 1 inch or wider. Around 6,750 linear feet of 1/4 inch cracks were crack filled. Two coats of MTR Master-Seal were applied over about 349,863 square feet. Finally, the area was re-striped to the original plan.

 

Owner

Breakthru Beverage

Location

Las Vegas, NV