Tempe Marketplace

Tempe, AZ

Cleaning, crack sealing, seal coating, and restriping were performed in 18 segments over the course of 18 consecutive days for Tempe Marketplace. This project required extensive communication and planning with the customer to achieve the best plan for traffic flow. All work had to be completed between 10:00 P.M. and 6:00 A.M., as the shopping complex remained open for the duration of the project.