Sunland completed the milling and paving work in the Islands community in two phases. Phase one was finished in May 2016 and involved 96,232 square yards of milling and 9,581 tons of paving. Phase two, scheduled for completion on July 31, 2017, included 107,012 square yards of milling and 10,538 tons of paving.